March 04 2000
'Force majeure' is a concept which is widely used in international construction
contracts. However, its meaning and effect can differ significantly between
one contract and another, and between one jurisdiction and another. This article
examine some of the features of force majeure provisions in construction
contracts.
English Law
Underlying the concept of force majeure is a contracting party's concern
that it should not be held to its obligations if performance is prevented by
unexpected or unforeseen circumstances outside its control. Under
English law, force majeure has been held to apply:
It includes the following events:
Subject to giving notices, a party who is prevented from performing any of
its obligations by force majeure is excused performance for as long as
the force majeure prevents it from performing. If the contractor is delayed
by force majeure, he is entitled to an extension of time. If the force
majeure (i) is any of the above events with the exception of natural catastrophes,
and (ii) with the exception of wars and hostilities, occurs in the country where the site
is located, the contractor is also entitled to be reimbursed for any additional
cost.
If the execution of the works is prevented for a continuous period of more than
84 days, or for multiple periods which total more than 140 days, then either
party may give notice terminating the contract. If the contract is terminated
the contractor is entitled to be paid for the following costs:
The FIDIC force majeure definition is wide. It must be an 'exceptional'
event beyond a party's control, but what constitutes 'exceptional' is open to
debate. The list of events included is illustrative only and does not necessarily
limit the general words of the definition.
Thus, if a sub-contractor defaults in the performance of its contract and the
contractor could not have prevented the default through skilful management,
the sub-contractor's default could fall within the force majeure clause
if it is exceptional and makes it impossible for the contractor to perform.
Similarly, if the employer retains the services of a designer to provide design
information on his behalf and the designer defaults in a major way, the employer
may be relieved of responsibility for providing this information on time. The
clause may also apply if the employer encounters exceptional difficulties in
providing access to the site, relieving the employer of responsibility, but
without compensating the contractor.
The clause could also cover matters such as the following:
In these cases, the party responsible for obtaining or maintaining the relevant
consent or approval or for securing performance by the utilities provider may
be relieved of responsibility under the force majeure clause.
Projects
The potential effect of the FIDIC force majeure clause is significant.
However, where FIDIC is to be used in the context of a limited recourse financed
project with high gearing and a single purpose project company, it is likely
that the clause will be modified to reflect the terms of the project agreement.
This agreement governs the project company's rights and obligations relating
to the construction and operation of the project.
Force majeure clauses in project agreements are often detailed and carefully
drafted. They frequently divide the force majeure events into two categories.
The first is political force majeure, that is, risks that generally relate
to changes in the political environment (embargoes, riot, insurrection and blockade,
terrorist actions and sometimes war) or legal environment (changes in law or
licences, permits and consents necessary for the project) in the country where
the project is located.
The second is non-political force majeure. These events are (i) physical risks that
might affect a project (eg, storm, tempest, earthquake, flood and other natural
catastrophic events) and (ii) events that fall within the definition of political
force majeure but which occur outside or do not directly involve the
country where the project is located.
On the occurrence of a non-political force majeure event, the project
company is entitled to an extension of the time for completion and relief from
termination. However the project company is not usually compensated for any
delay to its revenue stream that results from this delay in the works. The project
company may thus have no alternative but to seek liquidated damages from
the contractor to meet the shortfall. This means that the occurrence of a non-political
force majeure event does not entitle the contractor to any extension
of time under the construction contract. Thus, while the contractor may be given
some relief from termination, it remains liable to the project company for liquidated
damages.
By contrast, in the case of political force majeure, the project company
is generally entitled to both an extension of time and compensation. Since the
project company no longer needs the cashflow of liquidated damages to meet debt
service the contractor is in turn entitled to an extension of time and its
loss and expense under the construction contract.
Non-political force majeure can place the contractor in a very difficult
position. Sometimes the project agreement provides for the concession period
(rather than the date for completion of construction/commencement of operation)
to be extended where delay is caused by a non-political force majeure
event, but this is only a partial solution. Although it gives the project company
an additional opportunity to generate revenue from the project at the end of
the concession period, it does not solve the project company's immediate cashflow
problem at or near completion of construction.
Insurance may provide a partial solution. If the non-political force majeure
event is insurable (eg, fire or flood) then it may be possible to insure the
losses resulting from the delay under an advanced loss of profit policy, although
this cover will be subject to deductibles. If non-political force majeure
events are not insurable then it is necessary to specify the circumstances in
which either party can terminate. If the event is a catastrophic one, the period
of delay before termination can occur should be short. For lesser events, the
period should be longer.
Conclusion
The need for a carefully drafted and thoroughly worked-out force majeure
clause is essential for the success of a long-running project and this clause
will be followed very closely in the construction contract. In many jurisdictions
the force majeure clause will be central to the allocation of the risk
between the parties. An alternative is to adopt the approach of the PFI in the
UK. This is to define force majeure very narrowly so that the clause
is of less importance, but to include separate provisions dealing with other
risks and responsibilities using different terminology.
In all cases, however, these
issues should be clearly addressed and their consequences specifically provided
for.
For further information on this topic please contact Caroline Cummins at CMS Cameron McKenna by telephone (+44 20 7367 3000) or by fax (+44 20 7367 2000) or by e-mail (caroline.cummins@cmck.com). The CMS Cameron McKenna's web site can be accessed at www.cmck.com.
The materials contained on this web site are for general information purposes only and are subject to the disclaimer.
Comment or question for author
ILO provides online commentaries as specialist Legal Newsletters. Written in collaboration with over 500 of the world's leading experts and covering more than 100 jurisdictions, it delivers individually requested information via email to an influential global audience of law firm partners and international corporate counsel. Please click here to register for the service.
The materials contained on this website are for general information purposes only and are subject to the disclaimer.
ILO is a premium online legal update service for major companies and law firms worldwide. In-house corporate counsel and other users of legal services, as well as law firm partners, qualify for a free subscription. Register at www.iloinfo.com.