Introduction

On 5 May 2020 Parliament passed a law modernising environmental legislation and harmonising Greek law with EU Directives 2018/844/EU (amending the directives on the energy performance of buildings and energy efficiency) and 2019/692/EU (amending EU Directive 2009/73/EC concerning common rules for the internal market in natural gas). This new Law 4685/2020 (OJ A' 92/2020) contains legislative measures which will significantly amend, standardise and simplify the current licensing procedure for renewable energy power plants – particularly the procedure for obtaining a renewable energy source (RES) production licence and an environmental approval.

New RES production certificate

One of the most important changes introduced is the replacement of the production licence with a certificate. The Regulatory Authority for Energy (RAE) is authorised to issue these certificates, but the law provides for the possibility of a future ministerial decision delegating this authorisation to another person or authority.

Applications for issuing a certificate must be submitted via the electronic register, which will be established according to the provisions of the new law. Each year there will be three application rounds, which will take place during the first 10 days of February, June or October.

The new law envisages two different application procedures and subsequently two different types of certificate: one for special projects and one for all other RES projects.

The following projects are defined as 'special projects':

  • 'hybrid plants', as defined by law;
  • high-efficiency combined heat and power plants whose capacity exceeds 35MW;
  • geothermal power plants;
  • power plants which fall under the category of 'other RES plants' as provided for in Article 4 of Law 4414/2016 (eg, plants which use waste not included in other categories);
  • groups of wind parks whose total capacity exceeds 150MW;
  • solar thermal power production plants which are connected to the networks of the non-interconnected islands;
  • offshore wind parks;
  • RES plants which are connected to the grid through a separate submarine cable; and
  • hydroelectric plants whose capacity exceeds 15MW.

Of the two envisaged procedures, the procedure for obtaining a special project certificate will inevitably be more complex and time consuming, as more documents and studies will have to be prepared, submitted and reviewed. However, applicants will not be burdened with paying a levy for issuing such certificate.

The documents uploaded to the electronic register with the application for the issuing of the special project certificate should include:

  • a detailed technical description of the project;
  • capacity measurements (for wind plants);
  • an energy study and business plan. Particularly for hybrid plants, a technical financial study should be submitted, which should include an assessment of the energy efficiency of the project based on the relevant legislation and on the Non-interconnected Islands Operation Code;
  • data confirming the means of financing the project and technical capacities; and
  • a general business plan, which should refer to all of the applications made by the same applicant, for both certificates and special project certificates.

As noted above, applications for plants which do not belong to the category of special projects will be processed faster, but applicants should in addition to the levy for the application, paid by all applicants, pay a levy for the issuing of the certificate into the special RES account. The levy will depend on the plant capacity and will range from €3,000 per megawatt for plants with a capacity up to 1MW to €1,000 per megawatt for plants whose capacity exceeds 100MW. In any case, the levy will not exceed that which corresponds to a plant with a capacity of 250MW.

Both types of certificate will be issued for 25 years and may be renewed for another 25 years. Applicants must carry out the remaining licensing procedures and conclude a power purchase agreement within a reasonable timeframe. Otherwise, their certificate will automatically cease to be valid and the land location and grid capacity will be freed. Thus, a certificate will automatically expire if, for example, the holder (in the case of a photovoltaic or onshore wind plant) fails to:

  • obtain environmental approval within six months from the certificate's issuance; or
  • submit an application for the issuance of a binding offer for grid connection within 36 months from the certificate's issuance.

A regulation on the above licensing procedure is expected to be issued within three months of the law's adoption.

In cases of limited network or insufficient carrying capacity in a municipality or spatial overlapping of projects for which applications have been submitted during the same round, the RAE will request that the applicants concerned negotiate to resolve these issues. If this fails, the RAE will comparatively evaluate the applications based on certain criteria (eg, titles of land ownership or possession), which will be further specified in the forthcoming regulation. In cases of insufficient carrying capacity in a certain municipality, during the evaluation period, the RAE will not issue certificates for applications made during subsequent application rounds.

Simplified environmental licensing procedure

Further, the new law introduces various provisions that aim to simplify and expedite the environmental licensing procedure (including the renewal and amendment of the environmental approvals), as experience has shown that the respective deadlines envisaged in the pre-existing legal framework are seldom met. Thus, the environmental approvals will be valid for 15 years, instead of 10, on the condition that the circumstances under which they were issued remain unchanged. The deadlines for completing the environmental licensing process, with the exception of the public consultation deadlines, are significantly reduced, and certain stages of the procedure have been merged. It is also noteworthy that a request on behalf of the authorities for the submission of supplementary data by the applying project operator does not constitute a reason for the authorities to delay the evaluation of the file submitted.

Next legislation to be issued

According to the Ministry for Environment and Energy's announcement, this law was the first step in the government's strategy to simplify the development of RES in Greece. The next planned step is the simplification of the procedures for the issuing of two important licences – namely, for the establishment and operation of a plant. The law introducing these amendments is planned to be passed within the next three months.