Introduction

Throughout the COVID-19 pandemic, Italy has been one of the most affected nations worldwide. It is unsurprising that business relationships are facing unprecedented hurdles. Since the declaration of the state of emergency on 31 January 2020,(1) the government has enacted a series of restrictions, and issued different provisions, in relation to the COVID-19 pandemic.

This article focuses on case law and the courts' approaches towards the force majeure and hardship principles in contract law within the context of the COVID-19 pandemic.

Legal background

Article 91 of the Law-Decree 18 of 17 March 2020 (the so-called 'cura Italia decree') states that compliance with its provisions must always be considered when assessing a debtor's contractual liability pursuant to Articles 1218 and 1223 of the Civil Code.(2) Scholars and the Court of Cassation (in its 8 July 2020 report) have criticised Article 91 of the law-decree for its lack of clarity.(3) In particular, it is unclear why the article refers to Article 1218 of the Civil Code, which excludes the liability of a debtor in the event of impossibility of performance. In fact, if the pandemic were to make performance impossible, the debtor would be exempted anyway, and the new provision does not change that.(4) Moreover, such provision does not exclude ex lege the liability of the debtor, but merely defers to the judge the assessment of the relationship between compliance with the emergency provisions and non-compliance with the contractual obligations. Against this background, it is necessary to provide a brief assessment of the possible legal consequences (and remedies) at parties' disposal, especially in business relationships characterised by continuous performance for a prolonged period (eg, lease and rental agreements).

Tools at parties' disposal

The pandemic is causing several difficulties in the performance of contractual obligations. Legislatures worldwide are aware of the possibility that, due to some critical occurrences, contracting parties may be excused for their non-performance of the obligations. Contracting parties should, in the first instance, rely on contractual mechanisms included in their agreements. The two most relevant examples are force majeure and hardship.The two traditional examples in Italy are force majeure and hardship. Taking as example the recently adopted International Chamber of Commerce model clauses:

  • force majeure excuses the liability of the debtor on the occurrence of an event or circumstance that impedes a party from performing its contractual obligations if that party proves that:
    • such impediment is beyond its reasonable control;
    • the event or circumstance could not reasonably have been foreseen at the time of the conclusion of the contract; and
    • the effects of the impediment could not reasonably have been avoided or overcome by the affected party; and
  • hardship protects the disadvantaged party in situations where the event or circumstance has rendered the performance more onerous than it could have been foreseen at the time of the conclusion of the contract. On the occurrence of such event, and the proof that the debtor could not reasonably have avoided or overcome the event or its consequences, the parties are bound to negotiate alternative contractual terms. Should the parties eventually end up without an agreement, the original contract can be:
    • terminated;
    • adapted or terminated by a judge or arbitrator; or
    • terminated by a judge or arbitrator.

Case law

The case law available on this matter can be used to analyse questions such as how the Italian courts have used such remedies, and to what extent such remedies are available in the absence of an express clause in the agreement. This section will examine how the courts have used remedies to:

  • terminate contracts; and
  • to maintain contracts in force.

Termination of contracts

The Italian legal system provides for different remedies that, once triggered, are apt to terminate contracts – namely, the termination of contracts because of:

  • the absolute impossibility of performance (Article 1463 of the Civil Code); and
  • the supervening excessive onerousness of performance (Article 1467 of the Civil Code).

The first remedy resembles force majeure and the second resembles hardship. It is still unclear whether (and whether affirmative, to what extent) such remedies apply in the case of contractual relationships affected by the pandemic, particularly in the absence of specific contractual terms in the agreement. The Court of Cassation's report has found that neither remedy results in sufficient comfort.

As to the supervening impossibility of performance, it can be said that the pandemic did not render the performance impossible per se,(5) but merely (and not always) more difficult. However, it can be said that when the government addressed the pandemic through measures that (factually and legally) prohibited non-necessary activities, such measures constituted a factum principis, apt to excuse the non-performance.(6) However, even in such critical situations, it is unclear whether the remedy of termination because of the supervening impossibility of performance is adequate. The Court of Cassation's report noted (both generally and specifically referencing to rental agreements) that the performance of leasing a property remains possible even when the corresponding obligation results in a weakening of this right because of the factum principis.(7) In a controversial decision by the Rome Court,(8) the judge blatantly rejected the defendant's claim that it had been unable to pay rent because of a 72% decrease in revenue. After having confirmed that the pandemic cannot per se represent an impossibility, the judge proceeded by saying that only administrative acts could play a role.(9)

With regard to the supervening, excessive onerousness of performance, although it is probably (at least prima facie) a remedy more suitable to address the effects of the pandemic, it still does not convince judges(10) and scholars.(11) Pursuant to Article 1467 of the Civil Code, a contract may be terminated by the party whose performance has become excessively onerous because of unforeseen and extraordinary circumstances.(12) Paragraph 3 of Article 1467 states that termination cannot occur if the other party offers to equitably modify the contract.(13) However, such provision does not allow the disadvantaged party to request the reductio ad aequitatem, but rather only the termination.(14) Thus, it is a double-edged sword in the hands of such party, which cannot maintain the contract alive and request a modification. Therefore, as noted by the Court of Cassation's report, it is not the most suitable remedy for business relationships where the disadvantaged party actually needs to maintain the contract alive (with the modifications).(15)

Preservation of contracts: towards a duty to renegotiate?

Since the remedies which terminate contractual relationships are neither adequate nor (at least most of the time) in the interest of the parties, the fundamental question is whether the renegotiation of contractual terms is the solution. Moreover, if the latter question is answered affirmatively, do the parties have a duty to renegotiate?(16)

The Court of Cassation's report promotes the renegotiation of contractual terms – which is the 'translation' of the duty to renegotiate contained in hardship clauses – as the solution.(17) In particular, according to the report, the renegotiation of contractual terms comes within the sphere of application of the duty to perform contracts in good faith.(18) Thus, if a contract becomes excessively more onerous for one of the parties, good faith could impose to the parties (to try) to bring the contract within the boundaries agreed by the parties at the time of the conclusion of the contract.(19) Such argument has been brought before several courts in the context of pandemic-affected contractual relationships.(20) However, the courts have concluded with divergent positions. In certain cases, judges agreed that a general duty to renegotiate contractual terms exists, notwithstanding the language of Article 1467 of the Civil Code, which provides only for termination.(21) In other cases, judges plainly rejected the good-faith argument brought forward, stating that a provision which allows the disadvantaged party to request a renegotiation does not exist in the Italian legal system.(22)

Is there a duty to renegotiate?

Since it is impossible to force people to bargain, it should be impossible to oblige them to renegotiate.(23) Sophisticated business operators should have considered whether to include hardship clauses or other contractual mechanisms imposing renegotiation or alternative remedies other than termination in their contracts. The fact that they did not should be interpreted as a sign that they have agreed to bear the risk, possibly as a result of other strategies to insure or hedge against that risk. However, scholars have asserted that by limiting the remedies to the termination of contracts, the scope of contract law is thwarted as the latter will not redistribute the unforeseen events between the contracting parties, thus allowing situations of social contractual injustice.(24) The Court of Cassation's report is straightforward when it states that renegotiation, in the face of contingencies that alter contractual relationships, becomes an obligatory step.(25) Some courts have started to follow this position;(26) however, it remains to be seen whether this will be the path for the future.

Comment

When it comes to pandemic-affected contractual relationships, everything is up for grabs. On the one hand, there are the traditional remedies aimed at terminating the relationship when the performance of either party has become impossible or excessively onerous. On the other hand, the renegotiation may find its place within the legal system, thus aligning the Italian experience to that of other legal systems and international practice. Overall, recent experience has confirmed the critical importance of a well-drafted contract. Courts should be cautious about reading into the contract a clause that the parties could have inserted, but did not.

Endnotes

(1) Published in the Official Gazette on 1 February 2020, Number 26.

(2) For a detailed analysis, see S Monti, "L'inadempimento ai tempi del Covid: qualche riflessione sull'art. 91, D.L. n. 18/2020", Ilquotidianogiuridico, 2021.

(3) M Torsello and M M Winkler, "Coronavirus-infected international business transactions: a preliminary diagnosis", Diritto del Commercio Internazionale, fasc 3, 2020, p 851; S Leuzzi, "Novità normative sostanziali del diritto 'emergenziale' anti-Covid 19 in ambito contrattuale e concorsuale", in Ufficio del Massimario e del ruolo, Corte Suprema di Cassazione (the Court of Cassation's report), 8 July 2020, p 8: "[l]a norma è di ardua interpretazione". For a brief commentary of the Court of Cassation's report, see A Mager, S Addamo, F De Gottardo and C Gentile, B Bonfanti, "I principi della Cassazione sulle novità del diritto 'emergenziale' anti-Covid 19 in ambito contrattuale e concorsuale", dirittobancario.it, 2020.

(4) M Signorelli, "La locazione commerciale al tempo della pandemia: prime prospettive di sistema e soluzioni resilienti", Responsabilità Civile e Previdenza, 2020, fasc 5, p 1686.

(5) M Torsello, M M Winkler, p 848; M Meroni, "COVID-19: i possibili effetti della dichiarazione di pandemia sui contratti", 4clegal.com, 2020; Rome Court's 16 December 2020 decision:

ogni attività umana avrebbe potuto continuare a svolgersi regolarmente anche in periodo di emergenza sanitaria, con la sola differenza che il soggetto interessato avrebbe corso il rischio di contrarre il virus (così come, in modo diverso, il conducente che si pone alla guida accetta il rischio di essere coinvolto in un incidente mortale causato da altri, ipotesi che nella moltitudine dei casi è statisticamente certa).

Less drastic but arriving at the same conclusion are the Brescia Court's 11 August 2020 decision and the Milan Court's 10 June 2020 decision, with related note of V Sangiovanni, "Contratto di locazione commerciale, mancato pagamento dei canoni e inibitoria del pagamento della garanzia bancaria a causa del covid-19", Condominioelocazione.it, 2020.

(6) F Benatti, "Contratto e COVID-19: possibili scenari", Banca Borsa Titoli di Credito, 2020, fasc 2, p 201.

(7) Page 4 of the Court of Cassation's report states that:

[c]on maggiore difficoltà entro l'alveo applicativo dell'art. 1464 c.c. possono ricondursi i contratti di locazione, anche di beni produttivi, incisi dallo scotto della pandemia, dal momento che la prestazione di concessione in godimento rimane possibile e continua a essere eseguita quand'anche per factum principis le facoltà di godimento del bene risultino momentaneamente affievolite.

(8) Rome Court, 16 December 2020.

(9) Ibid:

[d]a ciò deriva che le dedotte conseguenze per l'istante non sono affatto riconducibili alla emergenza sanitaria in sé intesa, ma al complesso normativo provvedimentale che, su tale presupposto, è intervenuto sui diritti e sulle libertà dei cittadini, ivi compresi quelli dell'interessato istante.

(10) Pisa Court, 30 June 2020; incidenter tantum, Rome Court, 25 July 2020.

(11) M Signorelli, p 1696 ff; E Navarretta, "Giustizia contrattuale, giustizia inclusiva, prevenzione delle ingiustizie sociali", Giustizia Civile, 2020, fasc 2, p 248.

(12) See Article 1467(1) of the Civil Code:

se la prestazione di una delle parti è divenuta eccessivamente onerosa per il verificarsi di avvenimenti straordinari e imprevedibili(2), la parte che deve tale prestazione può domandare(3) la risoluzione del contratto.

(13) See Article 1467(3) of the Civil Code: "[l]a parte contro la quale è domandata la risoluzione può evitarla offrendo di modificare equamente le condizioni del contratto".

(14) M Signorelli, p 1697.

(15) Page 6 of the Court of Cassation's report: "[l]'emergenza non si tampona demolendo il contratto. Più che la liberazione del debitore-imprenditore dall'obbligazione, cruciali appaiono l'attenuazione o il ridimensionamento del contenuto di questa".

(16) V Carlesimo, "Il Covid 19 quale causa di inadempimento contrattuale", diritto.it, 2020. See also V Pandolfini, "L'impatto del Covid-19 sui contratti commerciali: la Cassazione promuove la rinegoziazione obbligatoria", Ilquotidianogiuridico.it, 2020.

(17) Page 19 ff of the Court of Cassation's report.

(18) Page 22 of the Court of Cassation's report: "[p]roprio la portata sistematica della buona fede oggettiva nella fase esecutiva del contratto ex art. 1375 c.c. assume assoluta centralità".

(19) The duty to renegotiate does not mean that the parties must agree on new contractual terms. Rather, it means that the parties must conduct the negotiations in good faith. See Page 24 ff of the Court of Cassation's report.

(20) See, for example, Rome Court, 27 August 2020; Milan Court, 21 October 2020; Rome Court, 15 January 2021.

(21) Rome Court, 27 August 2020:

qualora si ravvisi una sopravvenienza nel sostrato fattuale e giuridico che costituisce il presupposto della convenzione negoziale, quale quella determinata dalla pandemia del Covid-19, la parte che riceverebbe uno svantaggio dal protrarsi della esecuzione del contratto alle stesse condizioni pattuite inizialmente deve poter avere la possibilità di rinegoziarne il contenuto, in base al dovere generale di buona fede oggettiva (o correttezza) nella fase esecutiva del contratto (art. 1375 c.c.).

See the critical related note by M Di Marzio, "COVID-19: il giudice riduce il canone delle locazioni ad uso di ristorante", ilprocessocivile.it, 2020. Similarly, on 21 October 2020 the Milan Court – following the position adopted in the Court of Cassation's report – stated:

a causa dell'emergenza sanitaria in corso, è da ritenersi necessaria, alla luce del principio di buona fede e correttezza nonché dei doveri di solidarietà costituzionalizzati (art. 2 Cost.), una rinegoziazione del canone di locazione al fine di riequilibrare il sinallagma.

See, also for further references, the related note of P Scalettaris, "Necessaria la rinegoziazione del canone nel caso di morosità in tempi di emergenza?" Condominioelocazione.it, 2020.

(22) Rome Court, 15 January 2021.

(23) F Benatti, p 205.

(24) See the interview with V Roppo, who states that the pandemic should make people discover instruments aimed at maintaining contracts alive, rather than using the traditional instruments aimed at terminating contracts:

[c]ovid-19 segna il trionfo dei regimi delle sopravvenienze (impossibilità ed eccessiva onerosità sopravvenuta) e dell'inadempimento… Questo però vale nella sola misura in cui – di fronte a inadempimenti e soprattutto sopravvenienze – l'unico rimedio concepibile per affrontare questi fattori di disturbo del rapporto contrattuale sia lo scioglimento di questo. È la logica del codice. Ma è logica insufficiente, nel momento in cui emerge che in tante occasione il rimedio appropriato per gestire i disturbi del rapporto non è la sua cancellazione ma piuttosto la sua manutenzione con aggiustamenti.

(25) Page 24 of the Court of Cassation's report.

(26) Milan Court, 21 October 2020.