Introduction

This article explores some of the key issues facing vessel owners when bidding for and negotiating floating liquefied natural gas (LNG) projects, whether for floating liquefaction or floating storage and regasification units.

Often the procurement of a floating asset will be on a public or private competitive procurement basis and vessel owners will be asked to compete with others in the market. There are no hard and fast rules to the way in which these tenders are run and some will deal with much of the detail at the tender phase, while others will leave the heavy lifting to be handled in face-to-face (or, more commonly in these times, virtual) discussions with the short-listed bidder. The wordings of bid bonds will need to be carefully reviewed to ensure that these cannot be called on capriciously and any term sheets or letters of intent will need to be analysed for legally binding content.

Upfront costs

The documents that are needed in such projects are often complex and time consuming to negotiate. However, project timelines often cannot wait and require early expenditure on certain engineering and long-lead items in order to maintain the viability of the project. Thought must be given at an early stage as to how vessel owners can protect themselves in the event that they spend substantial sums before definitive project documents are signed. Bespoke arrangements are often entered into.

Newbuilding and conversion contracts

Regardless of whether a bespoke newbuilding is being constructed or an existing trading vessel is being converted, the parties will need to assess:

  • how much oversight and access the project developer will have in relation to the construction or conversion contract;
  • how free the owner will be to exercise its rights under that contract; and
  • what step-in rights the project developer will have in the event of a breach of the construction or conversion contract or the employment contract for the unit.

Delivery and acceptance

The delivery and acceptance regime is an important piece of the jigsaw and appropriate time in the discussions should be set aside for such discussions. There will usually be deadlines for:

  • the arrival of the unit at the project site; and
  • the passing of performance tests.

Failure to meet the deadlines will usually result in a liability of the owner for significant liquidated damages, unless they can point to a failure on the part of the project developer or a force majeure event. Bearing in mind the significant sunk costs expended by owners up to the point of the unit arriving at the project site, it will also be important for owners to start to receive an income stream as early as possible, to cover at least the operating expenses and the financing costs. This might be challenging for project sponsors who are yet to earn an income stream themselves from the project if the project infrastructure is not ready in time and an appropriate accommodation will need to be reached. Thought will also need to be given as to:

  • the point at which the project sponsors can terminate the lease or charter contract for delay in delivery or acceptance;
  • the damages which might flow from that; and
  • the ability to accept a deficient unit and on what basis.

Payment and performance

Once the unit has been accepted and is in service, the owners will normally be entitled to a daily rate to cover both capital expenditures and operating expenses. Detailed consideration will need to be given as to the basis on which that daily rate may be reduced or not apply, depending on the ability of the unit to perform the services required thereof. In regasification projects, the owners will often be asked to give performance warranties in respect of:

  • LNG loading rates (from a carrier to the unit);
  • the regasification flow rate and modulation;
  • fuel consumption; and
  • the specification of regasified LNG.

In liquefaction projects, relevant performance warranties will often relate to:

  • LNG unloading rates (from the unit to a carrier);
  • liquefaction rates;
  • LNG retainage; and
  • the specification of LNG sent out.

Prudent owners will seek to cap these liabilities and ensure that they are the sole remedies for the particular shortfall in performance.

Country issues

Unit owners must get on top of the local regulatory issues at an early stage as these can significantly add to the complexity and costs of any project. Having reliable local input throughout the process is key. Depending on the jurisdiction in question, import and export regimes can be burdensome, the tax landscape may be challenging and the regulatory and environmental issues should never be underestimated. There may also be political risks which will need to be factored in to the parties' thinking. Insurance advice at an early stage in the process is always helpful.

Limitations on liability

Simplistically, both parties will take responsibility for their own people and property (including pollution and contamination) and for liability to third parties arising out of the indemnifier's negligence. There will likely be a well-thought out consequential loss exclusion covering each party's group and an overall cap on the unit owner's liability. The devil is often in the detail of these provisions and warrants a careful review during the course of negotiations.

Financing

The ability of each party to finance their project scope is paramount and must always be borne in mind throughout negotiations to ensure that the final commercial deal reached between the parties is 'bankable'. Lenders will generally wish to have various standstill and step-in rights in the event of a breach by their borrower and time should always be allocated to deal with complex direct agreements between the project parties and their respective lenders.